National Wheel J & P – Dubai

The scope of work involved providing a pump station capable of pumping 48,000 cu.m/day from a standard 600 mm man hole and then to be pumped a total distance of 16.5 Km to the sewage treatment plant. ACTION installed HDPE line and a Tee connection to utilize the sewage line.

Ultrasonic flow meters were used to monitor the flow rates. The project operated for a period of over 1 year.